A data center can circulate water through its servers for years while losing very little to evaporation. A neighboring facility can cool similar servers with a closed loop of its own and still draw water every hot afternoon. The difference is what happens after the heat leaves the racks. An outdoor dry cooler can push it into the air without evaporating water. A cooling tower can use evaporation to do the same job under conditions that make dry cooling harder. Both facilities could accurately describe their racks as liquid-cooled.
That distinction matters when a project advertises low water use or a community tries to decide how much capacity to set aside. A September paper in Environmental Science & Technology, reported by The Washington Post on November 9, put the siting question in perspective. The researchers placed 9,347 identified data centers on a map and found that 2,315 were in areas with at least one month of modeled water shortfall under 2001–2010 hydrologic conditions. The finding describes exposure across a mapped inventory of facilities. Each project still needs its own water accounting.
Three pieces of evidence make a cooling claim useful. Ask how the building rejects heat when the weather is hottest, how much water it draws and consumes at the site, and how the cooling choice changes electricity use. Each answer has a different bearing on the people who share the water supply and the grid.
Follow the heat from the chip to the outdoors
A processor's electricity input ends up largely as heat inside the server. In an air-cooled rack, fans move air past hot components. The warmed air then needs somewhere to go. An air-handling unit might pass it over a coil connected to another cooling loop. Where outside conditions allow, an economizer can reduce or bypass mechanical refrigeration. Servers described as air-cooled can therefore belong to a building that uses water at a later stage.
Direct-to-chip liquid cooling moves heat out of a high-density rack using coolant circulating through cold plates attached to selected components. A heat exchanger can transfer this energy from the rack circuit to a separate building loop while keeping the fluids apart. Fans may still cool other components or equipment. Liquid cooling can let operators carry more heat away from a crowded rack. What happens outdoors depends on the temperature of the fluid, the weather and the equipment available to take heat from the building loop.
At that point the three common choices have different costs. A dry cooler uses fans to move outside air across a radiator-like coil. The fluid stays inside, and heat passes through the metal. As outside air gets hotter, the unit has less temperature difference to work with. A design can accommodate that with more heat exchanger surface, a warmer coolant loop, additional refrigeration or other operating changes. The effect on electricity depends on the complete system and the equipment's temperature limits.
An evaporative cooling tower transfers heat to air as some circulating water evaporates. This can achieve lower water temperatures than a comparable dry system under suitable weather conditions. The effective limit depends on humidity as well as temperature. The facility needs makeup water to replace evaporation. It also typically drains some concentrated water to control the buildup of dissolved minerals. The U.S. Department of Energy’s cooling guide describes these streams and the options for reducing makeup demand. A municipal utility still has to deliver the makeup water, including the portion that may later go to a wastewater system.
A hybrid system changes its mix according to the weather or the heat load. It might run mainly dry during cooler months and switch to evaporation in hot conditions. That can reduce annual water demand while keeping a substantial hot-day requirement. Ask which operating mode the site assumes during its hottest design day and when primary equipment is out of service. A backup mode matters if it needs water the supplier will struggle to deliver during the same heat event.
What a real cooling retrofit can tell us
A documented retrofit in Golden, Colorado, shows how far the hybrid approach can go. In 2016, the National Renewable Energy Laboratory added a dry thermosyphon cooler to its high-performance computing facility alongside existing towers and heat recovery. The team reported a first-year on-site water-use intensity of 0.70 liters per kilowatt-hour of IT energy. Its estimated comparison for continuing with towers and heat recovery was 1.27 liters per kilowatt-hour. The project team attributed about 7,950 cubic meters of savings to the retrofit across its first two years.
The 2018 technical report gives readers two reasons to be careful about transferring that result. The comparison is a counterfactual calculated from site data. The machine room also already ran warm-water cooling and reused some heat in the building. In the first year, the cooling towers still handled 47% of the total heat rejection. The result shows what one hybrid design made possible at a particular facility. To use it as a planning precedent, compare climate, loop temperatures, IT demand and how often the wet equipment still runs.
Microsoft offers a different reference point. In June 2026 the company described a direct-to-chip design intended to operate without evaporating cooling water. That claim has a specific boundary. A building can still draw water for restrooms, maintenance or other uses. A region containing several Microsoft facilities can also have a mixture of designs. The evidence a permitting authority or cloud customer would need is the site's actual operating configuration and metered use across the reporting period.
Read the water meter and the power bill together
Water usage effectiveness, or WUE, usually relates site water use to IT electricity use in liters per kilowatt-hour. Ask for the underlying volumes, the equipment energy in the denominator, and what the operator counts as site water. Evaporation, discharge and potable water are different things to track. A withdrawal records water taken from a source. Consumption records the part unavailable for reuse at the relevant place and time, for example because it evaporated. A recycled supply can reduce demand for drinking water while the equipment continues to evaporate water at a similar rate.
Power usage effectiveness, or PUE, divides facility electricity use by IT electricity use over the same period. It shows how much overhead sits above the IT load. It cannot tell you how much useful work the servers deliver or whether marginal electricity generation draws on the same watershed. A development can improve both intensity ratios while using more electricity and water overall if it adds enough computing capacity. Total annual volumes and peak demands belong beside the ratios.
Consider an illustrative facility running an average IT load of 20 megawatts all year, equivalent to 175.2 gigawatt-hours of IT energy. Give one cooling design a PUE of 1.20 and the other a PUE of 1.28. The higher-PUE design then needs about 14 additional gigawatt-hours a year for the same IT load. Suppose it also lowers direct consumption from 0.60 to 0.05 liters per IT kilowatt-hour, saving about 96 million liters at the site. In this simplified example, additional power generation would have to consume about 6.9 liters per extra kilowatt-hour to offset the saved volume. The values are illustrative design assumptions. A real comparison needs the expected operating load and site-specific cooling performance.
A University of Michigan preprint worked through the geographic question with an hourly model of generator dispatch. For its fixed 200-megawatt IT case, an air-cooled chiller increased simulated electricity use by 32% compared with a water-cooled chiller and increased consumption at generators. The model still found 44% lower combined water consumption because the on-site savings were larger. That is a result for one set of equipment assumptions and one grid model. The study used estimated cooling metrics and simplified some operating controls.
Equal volumes in different places can have different consequences. The generation behind the additional power can change by hour and season, and a plant supplying the grid can draw water from a different basin. A modeled annual grid average can help estimate a footprint. A planner deciding how the two designs affect a hot summer afternoon needs to know where the extra electricity is likely to come from during those hours. Keep both results visible, because a local water saving can matter even when some consumption moves elsewhere.
Put the summer peak in the permit
A regional assessment by the Interstate Commission on the Potomac River Basin illustrates why an annual average can give a water supplier the wrong planning number. Its estimate for direct consumptive use within the Washington metropolitan area in 2025 was roughly 4 million U.S. gallons per day on average and about 15 million on a peak day. This is an estimate for a regional group of facilities, with a mix of designs. It is useful because the times when cooling demand is high can also be the times when rivers run lower and other customers need more water.
Water source deserves its own line. The City of Gilroy’s project account for a planned AWS data center in California estimates about 23 acre-feet of potable water per year initially and about 2 after the recycled-water connection. The figures describe projected drinking-water use. They leave a separate question about total volume and about the period before the pipe is ready. For that transition, the most useful documents specify when the connection must happen, what the project may do before it does and what the utility can provide during drought.
The global map puts cases like these on a broader scale. Its cells are approximately 50 kilometers wide near the equator, and its model estimates available water and existing sectoral demand. The underlying inventory lacks the facility detail needed to work out each site's cooling consumption. Reservoir operations or transfers can also alter local availability. Treat the map as a reason to ask better siting questions, then use the local water balance, permit and operating records to answer them. The Post's reporting made the same distinction between exposure and causation when it covered the paper in November.
What evidence to ask for
A proposal, sustainability report or cloud procurement response becomes much easier to evaluate when it answers a few concrete questions.
- Where does the heat go on the design day? Request the normal and backup cooling modes, their water sources, and the temperatures that trigger a switch.
- How much water is drawn and consumed? Ask for annual totals, monthly values and the peak-day requirement, with separate figures for potable and recycled supply. Get a definition of what each meter covers.
- How much electrical load moves to the grid? Compare like-for-like IT loads, facility power during heat events and assumptions about which generators serve the increased demand.
- Which numbers are predictions? Require the operating assumptions behind a promised figure and look for actual reporting after commissioning. Keep the first year of partial operation separate from a mature site's use.
- Who carries the risk when plans change? Identify any dependency on a future pipe or power connection, what happens during drought restrictions, and when the operator has to report against the design values.
The most informative number in a project hearing may be the water required on its hottest expected day, paired with the electrical load at the same hour. The engineering question belongs in the same discussion as the utility question. A credible claim connects the equipment inside the rack to the actual resource the community has to supply outside the fence.
Sources & Methods
Lumacta read the journal paper, federal cooling guidance, an engineering field report, a grid-model preprint and local planning documents. Company claims are attributed. The worked calculation uses illustrative inputs. Prepared with AI assistance.
- Global data center water-stress exposure study — Peer-reviewed location overlay using an inventory of facilities and a regional hydrological model.
- The Washington Post’s November coverage of the water-stress study — Independent reporting on the paper, including perspective from a researcher outside the study.
- U.S. Department of Energy guidance on data center cooling water — Federal engineering guidance on towers, alternative cooling, site water use and energy overhead.
- NREL field report on its Golden cooling retrofit — Project team’s monitoring results and estimated comparison for the first two years of operation.
- Microsoft’s June 2026 account of water efficiency and cooling — Company description of its cooling systems and the boundary of its zero-evaporation design.
- University of Michigan model of cooling and generator water use — Preprint comparing cooling configurations against simulated generator dispatch and regional water conditions.
- Potomac River Basin commission’s data center water assessment — Regional planning analysis of average and peak consumptive use.
- City of Gilroy project water questions and answers — Municipal planning estimates and conditions for switching industrial and irrigation water to recycled supply.